TSPLOSTProjects

Project ID MIL- 15
Local ID MIL-010
Project Name Title Freemanville Road at Redd Road Intersection Improvements
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Milton
Current Stage Design
Project Description Operational improvements at the intersection that may include turn lanes, traffic signal, or roundabout
Construction Firm Selected NULL
Design Firm Selected KCI
Estimated Design Completion Date August, 2026
Estimated Start Date For Project April, 2021
Estimated Construction Completion Date July, 2028
Estimated Substantial Completion Date July, 2028
Link To External Website https://cleargov.com/georgia/fulton/city/milton/projects/1208/freemanville-road-at-redd-road-_-tsplost
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,020,000
TSPLOST Dollars Spent ($) $83,991
TSPLOST Dollars Committed (not spent) ($) $936,009
Cost Status Green
Schedule Status Green
Status Active
Editor kathy.stallard@miltonga.gov
Project Year NULL
Last Update 2026-02-27 09:08:02
State NULL
Address NULL
Creation Date NULL