| Project ID | FA- 15 |
| Local ID | 25-004 |
| Project Name Title | Duncan Park Road, New Location Roadway Project |
| Tier | Tier 1 |
| Project Type | Roadway Projects |
| Initiatve Type | TSPLOST |
| City | Fairburn |
| Current Stage | Construction |
| Project Description | Extension of Park Road to provide a secondary entrance/exit into Clarence Duncan Park. REBID IFB: November 12th, 2025 Bid Opening: December 19th, 2025; 18 bids received. Low bidder: Piedmont Paving, Inc. for $4,566,732.55 NTP: March 16th, 2026 All work associated with the Duncan Park Road Project to be completed within three hundred and sixty (360) calendar days of the NTP. |
| Construction Firm Selected | Piedmont Paving, Inc. |
| Design Firm Selected | Southeastern Engineering, Inc. |
| Estimated Design Completion Date | November, 2025 |
| Estimated Start Date For Project | March, 2026 |
| Estimated Construction Completion Date | May, 2027 |
| Estimated Substantial Completion Date | March, 2027 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $722,685 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $722,685 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | lthompson@fairburn.com |
| Project Year | 2026 |
| Last Update | 2026-08-27 08:24:38 |
| State | GA |
| Address | NULL |
| Creation Date | NULL |