TSPLOSTProjects

Project ID FA- 12
Local ID 19-002
Project Name Title Roadway Improvements on Various City Roads Project
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City Fairburn
Current Stage Completed
Project Description City-Wide Resurfacing, 2019 Roadway Improvements on Various City Roads Project
Construction Firm Selected Shepco Paving, Inc.
Design Firm Selected In-House
Estimated Design Completion Date June, 2023
Estimated Start Date For Project August, 2019
Estimated Construction Completion Date December, 2019
Estimated Substantial Completion Date December, 2019
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $544,894
TSPLOST Dollars Spent ($) $463,461
TSPLOST Dollars Committed (not spent) ($) $81,433
Cost Status Green
Schedule Status Green
Status Active
Editor lthompson@fairburn.com
Project Year 2019
Last Update 2020-12-17 13:31:23
State NULL
Address NULL
Creation Date NULL