| Project ID | MIL- 7 |
| Local ID | MIL-004 |
| Project Name Title | Freemanville Road at Birmingham Road Intersection Improvements |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Milton |
| Current Stage | Completed |
| Project Description | Operational improvements that will address the all way stop controlled intersection and may include turn lanes, traffic signal or roundabout |
| Construction Firm Selected | NULL |
| Design Firm Selected | CHA |
| Estimated Design Completion Date | December, 2021 |
| Estimated Start Date For Project | March, 2020 |
| Estimated Construction Completion Date | September, 2023 |
| Estimated Substantial Completion Date | September, 2023 |
| Link To External Website | https://cleargov.com/georgia/fulton/city/milton/projects/1205/freemanville-road-at-birmingham-road-_-tsplost |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,990,000 |
| TSPLOST Dollars Spent ($) | $300,738 |
| TSPLOST Dollars Committed (not spent) ($) | $1,689,262 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | kathy.stallard@miltonga.gov |
| Project Year | NULL |
| Last Update | 2026-02-27 09:12:07 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |