| Project ID | EP- 20 |
| Local ID | EP-216 |
| Project Name Title | Ben Hill Rd (South) Sidewalks and Traffic Calming |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | East Point |
| Current Stage | Construction |
| Project Description | Ben Hill Road (Will Lee Road to Unincorporated Fulton County) Traffic Calming and sidewalks |
| Construction Firm Selected | Sol Construction, LLC |
| Design Firm Selected | Southeastern Engineers |
| Estimated Design Completion Date | June, 2021 |
| Estimated Start Date For Project | October, 2021 |
| Estimated Construction Completion Date | February, 2022 |
| Estimated Substantial Completion Date | February, 2022 |
| Link To External Website | www.eastpointcity.org |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $712,500 |
| TSPLOST Dollars Spent ($) | $441,074 |
| TSPLOST Dollars Committed (not spent) ($) | $271,426 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | guest |
| Project Year | 2021 |
| Last Update | 2021-10-11 22:23:41 |