Project ID EP- 19
Local ID EP-215
Project Name Title Pedestrian/Bike Projects
Tier Tier 2
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City East Point
Current Stage Land
Project Description Pedestrian/Bike Projects in City of East Point - Redwine Road (City of Atlanta to North Commerce Drive) This is a combined project EP-215 and EP-325 EP-215 $218,000 EP- 325 $350,000 Total project cost $568,000
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date February, 2020
Estimated Start Date For Project August, 2021
Estimated Construction Completion Date April, 2022
Estimated Substantial Completion Date December, 2021
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $218,000
TSPLOST Dollars Spent ($) $22,132
TSPLOST Dollars Committed (not spent) ($) $195,868
Cost Status Green
Schedule Status Yellow
Status Active
Editor JREEVES@EASTPOINTCITY.ORG
Project Year 2020
Last Update 2021-02-01 23:51:26