| Project ID | CH- 5 |
| Local ID | CH-202 |
| Project Name Title | Maintenance and Safety Enhancements |
| Tier | Tier 1 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST |
| City | Chattahoochee Hills |
| Current Stage | Construction |
| Project Description | This project consists of deep patching South Fulton Parkway at the bridge/County line, Two locations on Campbellton-Redwine (approx. 1,000 lf), Cochran Mill @ Woodruff, Rivertown @ Campbellton-Redwine, Complete work begun on Rivertown, Hutcheson Ferry (approx. 1,000 lf). Crack sealing South Fulton Parkway (areas not addressed by GDOT), Hutcheson Ferry (from The Inn to Cochran Mill), Campbellton-Redwine, and striping South Fulton Parkway, Hutcheson Ferry, Rico Road (southern portion), Cochran Mill Road, Rivertown Road and Campbellton-Redwine |
| Construction Firm Selected | ER Snell |
| Design Firm Selected | DWS |
| Estimated Design Completion Date | August, 2021 |
| Estimated Start Date For Project | September, 2021 |
| Estimated Construction Completion Date | November, 2021 |
| Estimated Substantial Completion Date | December, 2021 |
| Link To External Website | www.chatthillsga.us |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,251,765 |
| TSPLOST Dollars Spent ($) | $1,211,895 |
| TSPLOST Dollars Committed (not spent) ($) | $39,870 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | robbie.rokovitz@chatthillsga.us |
| Project Year | 2021 |
| Last Update | 2021-12-13 18:29:16 |