Project ID CH- 5
Local ID CH-202
Project Name Title Maintenance and Safety Enhancements
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City Chattahoochee Hills
Current Stage Construction
Project Description This project consists of deep patching South Fulton Parkway at the bridge/County line, Two locations on Campbellton-Redwine (approx. 1,000 lf), Cochran Mill @ Woodruff, Rivertown @ Campbellton-Redwine, Complete work begun on Rivertown, Hutcheson Ferry (approx. 1,000 lf). Crack sealing South Fulton Parkway (areas not addressed by GDOT), Hutcheson Ferry (from The Inn to Cochran Mill), Campbellton-Redwine, and striping South Fulton Parkway, Hutcheson Ferry, Rico Road (southern portion), Cochran Mill Road, Rivertown Road and Campbellton-Redwine
Construction Firm Selected ER Snell
Design Firm Selected DWS
Estimated Design Completion Date August, 2021
Estimated Start Date For Project September, 2021
Estimated Construction Completion Date November, 2021
Estimated Substantial Completion Date December, 2021
Link To External Website www.chatthillsga.us
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,251,765
TSPLOST Dollars Spent ($) $1,211,895
TSPLOST Dollars Committed (not spent) ($) $39,870
Cost Status Green
Schedule Status Green
Status Active
Editor robbie.rokovitz@chatthillsga.us
Project Year 2021
Last Update 2021-12-13 18:29:16