TSPLOSTProjects

Project ID UC- 10
Local ID US-109
Project Name Title Quick Response Projects
Tier Tier 1
Project Type Quick Response
Initiatve Type TSPLOST
City Union City
Current Stage Completed
Project Description Quick Response Projects in Union City - Quick Response Projects
Construction Firm Selected The Corbett Group
Design Firm Selected Atlas
Estimated Design Completion Date March, 2019
Estimated Start Date For Project April, 2019
Estimated Construction Completion Date August, 2019
Estimated Substantial Completion Date August, 2019
Link To External Website https://www.unioncityga.org/departments/public-services/capital-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $235,687
TSPLOST Dollars Spent ($) $107,077
TSPLOST Dollars Committed (not spent) ($) $128,610
Cost Status Green
Schedule Status Green
Status Active
Editor Lonnie Ferguson
Project Year NULL
Last Update 2023-02-27 15:31:46
State NULL
Address NULL
Creation Date NULL