TSPLOSTProjects

Project ID UC- 9
Local ID UC-108
Project Name Title Pedestrian/Bike/Landscape/Streetscape
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Union City
Current Stage Completed
Project Description Pedestrian/Bike/Landscape/Streetscape in Union City - Lower Dixie Lake Rd Sidewalks
Construction Firm Selected Magnum Paving
Design Firm Selected Atlas
Estimated Design Completion Date August, 2022
Estimated Start Date For Project September, 2022
Estimated Construction Completion Date November, 2022
Estimated Substantial Completion Date December, 2022
Link To External Website https://www.unioncityga.org/departments/public-services/capital-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $203,500
TSPLOST Dollars Spent ($) $904,300
TSPLOST Dollars Committed (not spent) ($) $-700,800
Cost Status Red
Schedule Status Green
Status Active
Editor Lonnie Ferguson
Project Year 2022
Last Update 2023-02-27 15:25:30
State NULL
Address NULL
Creation Date NULL