| Project ID | UC- 8 |
| Local ID | UC-107 |
| Project Name Title | Pedestrian/Bike/Landscape/Streetscape |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Union City |
| Current Stage | Completed |
| Project Description | Pedestrian/Bike/Landscape/Streetscape in Union City - Christian City Multi-Use Trail |
| Construction Firm Selected | Sol Construction |
| Design Firm Selected | Lowe Engineers |
| Estimated Design Completion Date | May, 2022 |
| Estimated Start Date For Project | June, 2022 |
| Estimated Construction Completion Date | November, 2022 |
| Estimated Substantial Completion Date | December, 2022 |
| Link To External Website | https://www.unioncityga.org/departments/public-services/capital-projects |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $525,000 |
| TSPLOST Dollars Spent ($) | $1,141,187 |
| TSPLOST Dollars Committed (not spent) ($) | $-616,187 |
| Cost Status | Red |
| Schedule Status | Green |
| Status | Active |
| Editor | lferguson@unioncityga.org |
| Project Year | 2022 |
| Last Update | 2023-02-27 15:31:26 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |