TSPLOSTProjects

Project ID UC- 8
Local ID UC-107
Project Name Title Pedestrian/Bike/Landscape/Streetscape
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Union City
Current Stage Completed
Project Description Pedestrian/Bike/Landscape/Streetscape in Union City - Christian City Multi-Use Trail
Construction Firm Selected Sol Construction
Design Firm Selected Lowe Engineers
Estimated Design Completion Date May, 2022
Estimated Start Date For Project June, 2022
Estimated Construction Completion Date November, 2022
Estimated Substantial Completion Date December, 2022
Link To External Website https://www.unioncityga.org/departments/public-services/capital-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $525,000
TSPLOST Dollars Spent ($) $1,141,187
TSPLOST Dollars Committed (not spent) ($) $-616,187
Cost Status Red
Schedule Status Green
Status Active
Editor lferguson@unioncityga.org
Project Year 2022
Last Update 2023-02-27 15:31:26
State NULL
Address NULL
Creation Date NULL