| Project ID | UC- 7 |
| Local ID | UC-106 |
| Project Name Title | Operations and Safety |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Union City |
| Current Stage | Design |
| Project Description | Operations and Safety in Union City - Goodson Rd from Union City Limits to Jonesboro Rd |
| Construction Firm Selected | Backbone Infrastructure |
| Design Firm Selected | Keck & Wood, Inc |
| Estimated Design Completion Date | January, 2022 |
| Estimated Start Date For Project | July, 2022 |
| Estimated Construction Completion Date | March, 2023 |
| Estimated Substantial Completion Date | April, 2023 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $588,000 |
| TSPLOST Dollars Spent ($) | $489,260 |
| TSPLOST Dollars Committed (not spent) ($) | $98,740 |
| Cost Status | Red |
| Schedule Status | Green |
| Status | Active |
| Editor | lferguson@unioncityga.org |
| Project Year | 2023 |
| Last Update | 2023-02-27 15:15:05 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |