Project ID UC- 6
Local ID UC-105
Project Name Title Londonderry Way Resurfacing and Streetscape
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Union City
Current Stage Construction
Project Description Operations and Safety in Union City - Londonderry Way Streetscape Improvements (SR 138 to Mall Blvd)
Construction Firm Selected CMC, Inc.
Design Firm Selected Atlas
Estimated Design Completion Date September, 2024
Estimated Start Date For Project February, 2025
Estimated Construction Completion Date August, 2026
Estimated Substantial Completion Date September, 2026
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $566,210
TSPLOST Dollars Spent ($) $871,360
TSPLOST Dollars Committed (not spent) ($) $-305,150
Cost Status Red
Schedule Status Red
Status Active
Editor lferguson@unioncityga.org
Project Year 2026
Last Update 2026-08-25 13:03:57
State Georgia
Address City of Union City
Creation Date 2026-08-25