TSPLOSTProjects

Project ID UC- 6
Local ID UC-105
Project Name Title Operations and Safety
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Union City
Current Stage Design
Project Description Operations and Safety in Union City - Londonderry Way (SR 138 to Mall Blvd)
Construction Firm Selected TBD
Design Firm Selected Atlas
Estimated Design Completion Date August, 2022
Estimated Start Date For Project September, 2023
Estimated Construction Completion Date July, 2024
Estimated Substantial Completion Date August, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $566,210
TSPLOST Dollars Spent ($) $104,761
TSPLOST Dollars Committed (not spent) ($) $461,449
Cost Status Yellow
Schedule Status Red
Status Active
Editor Lonnie Ferguson
Project Year 2023
Last Update 2023-02-27 15:11:34