| Project ID | UC- 5 |
| Local ID | UC-104 |
| Project Name Title | Operations and Safety |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Union City |
| Current Stage | Design |
| Project Description | Operations and Safety in Union City - Lancaster Lane (Shannon Pkwy to Shannon Way) |
| Construction Firm Selected | TBD |
| Design Firm Selected | Atlas |
| Estimated Design Completion Date | April, 2023 |
| Estimated Start Date For Project | September, 2024 |
| Estimated Construction Completion Date | April, 2023 |
| Estimated Substantial Completion Date | May, 2023 |
| Link To External Website | https://www.unioncityga.org/departments/public-services/capital-projects |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $274,010 |
| TSPLOST Dollars Spent ($) | $30,186 |
| TSPLOST Dollars Committed (not spent) ($) | $243,824 |
| Cost Status | Gray |
| Schedule Status | Gray |
| Status | Inactive |
| Editor | lferguson@unioncityga.org |
| Project Year | 2023 |
| Last Update | 2023-02-27 15:31:06 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |