Project ID UC- 2
Local ID UC-101
Project Name Title Congestion Relief/Roadway Projects
Tier Tier 1
Project Type Congestion Relief
Initiatve Type TSPLOST
City Union City
Current Stage Design
Project Description Congestion Relief in Union City - I-85/SR 138 Interchange (PARTIAL FUNDING)
Construction Firm Selected TBD
Design Firm Selected WSP USA
Estimated Design Completion Date August, 2023
Estimated Start Date For Project December, 2023
Estimated Construction Completion Date December, 2025
Estimated Substantial Completion Date November, 2025
Link To External Website http://www.dot.ga.gov
Primary Funding Source Sales Tax
TSPLOST Budget ($) $5,000,000
TSPLOST Dollars Spent ($) $1,065,284
TSPLOST Dollars Committed (not spent) ($) $3,934,716
Cost Status Green
Schedule Status Red
Status Active
Editor Lonnie Ferguson
Project Year 2026
Last Update 2023-02-27 15:30:54