| Project ID | EP- 12 |
| Local ID | EP-180 |
| Project Name Title | EP PATH Master Trail System |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | East Point |
| Current Stage | Completed |
| Project Description | Pedestrian/Bike Projects in City of East Point - Master Trail System |
| Construction Firm Selected | Lewallen |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | August, 2018 |
| Estimated Start Date For Project | February, 2019 |
| Estimated Construction Completion Date | July, 2020 |
| Estimated Substantial Completion Date | June, 2020 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $2,949,652 |
| TSPLOST Dollars Spent ($) | $2,949,652 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | chall@eastpointcity.org |
| Project Year | 2018 |
| Last Update | 2021-10-13 15:15:06 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |