Project ID EP- 9
Local ID EP-101
Project Name Title Bonnybrooke Way Resurfacing
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City East Point
Current Stage Completed
Project Description Maintenance and Safety Enhancements in City of East Point -Resurfacing. Bonnybrooke Way (see EP - 006)
Construction Firm Selected Mullin's Brothers Paving
Design Firm Selected Griffin & Davis Consulting
Estimated Design Completion Date January, 2020
Estimated Start Date For Project April, 2020
Estimated Construction Completion Date November, 2020
Estimated Substantial Completion Date November, 2020
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $103,000
TSPLOST Dollars Spent ($) $10,300
TSPLOST Dollars Committed (not spent) ($) $92,700
Cost Status Green
Schedule Status Green
Status Active
Editor guest
Project Year 2020
Last Update 2021-08-17 20:28:26