| Project ID | CSS- 32 |
| Local ID | TS172 |
| Project Name Title | Brandon Mill Road - Lost Forest Dr. to Brandon Ridge Dr. |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Connect the sidewalk system on east side of Brandon Mill Road from Lost Forest Drive to Brandon Ridge Dr |
| Construction Firm Selected | NULL |
| Design Firm Selected | NV5 |
| Estimated Design Completion Date | October, 2021 |
| Estimated Start Date For Project | December, 2019 |
| Estimated Construction Completion Date | May, 2025 |
| Estimated Substantial Completion Date | May, 2025 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $466,403 |
| TSPLOST Dollars Spent ($) | $474,840 |
| TSPLOST Dollars Committed (not spent) ($) | $-8,437 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2025 |
| Last Update | 2024-10-18 16:02:27 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |