TSPLOSTProjects

Project ID CSS- 32
Local ID TS172
Project Name Title Brandon Mill Road - Lost Forest Dr. to Brandon Ridge Dr.
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Sandy Springs
Current Stage Completed
Project Description Connect the sidewalk system on east side of Brandon Mill Road from Lost Forest Drive to Brandon Ridge Dr
Construction Firm Selected NULL
Design Firm Selected NV5
Estimated Design Completion Date October, 2021
Estimated Start Date For Project December, 2019
Estimated Construction Completion Date May, 2025
Estimated Substantial Completion Date May, 2025
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $466,403
TSPLOST Dollars Spent ($) $474,840
TSPLOST Dollars Committed (not spent) ($) $-8,437
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2025
Last Update 2024-10-18 16:02:27
State NULL
Address NULL
Creation Date NULL