| Project ID | CSS- 31 |
| Local ID | TS171 |
| Project Name Title | Roberts Drive (Ex. Walk S of Northridge Rd to Ex. Walk at Davis Academy) |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Connect the sidewalk system on east side of Roberts Drive from Northridge to Davis Academy |
| Construction Firm Selected | SD&C |
| Design Firm Selected | Calyx |
| Estimated Design Completion Date | July, 2020 |
| Estimated Start Date For Project | February, 2019 |
| Estimated Construction Completion Date | January, 2022 |
| Estimated Substantial Completion Date | July, 2021 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $446,377 |
| TSPLOST Dollars Spent ($) | $446,377 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2021 |
| Last Update | 2022-07-29 18:04:05 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |