TSPLOSTProjects

Project ID CSS- 30
Local ID TS170
Project Name Title Interstate North Pkwy - Chattahoochee River to Northside Drive
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Sandy Springs
Current Stage Completed
Project Description Sidepath system on north side of Interstate Pkwy from the park to Northside Drive
Construction Firm Selected CMES
Design Firm Selected Atkins
Estimated Design Completion Date October, 2020
Estimated Start Date For Project March, 2019
Estimated Construction Completion Date November, 2022
Estimated Substantial Completion Date November, 2022
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,646,272
TSPLOST Dollars Spent ($) $2,436,362
TSPLOST Dollars Committed (not spent) ($) $209,910
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2022
Last Update 2023-01-27 22:10:38
State NULL
Address NULL
Creation Date NULL