| Project ID | CSS- 29 |
| Local ID | TS169 |
| Project Name Title | Dunwoody Club Dr. - Spalding to exsiting walk at Fenimore Circle |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Connect the sidewalk system on east side of Dunwoody Club Drive from existing sidewalk to Spalding Dr |
| Construction Firm Selected | CMES |
| Design Firm Selected | Calyx |
| Estimated Design Completion Date | July, 2020 |
| Estimated Start Date For Project | March, 2019 |
| Estimated Construction Completion Date | May, 2022 |
| Estimated Substantial Completion Date | May, 2022 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,165,000 |
| TSPLOST Dollars Spent ($) | $1,036,283 |
| TSPLOST Dollars Committed (not spent) ($) | $128,717 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2022 |
| Last Update | 2023-01-27 22:08:43 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |