| Project ID | CSS- 27 |
| Local ID | TS167 |
| Project Name Title | Brandon Mill Road - Marsh Creek to Lost Forest Dr. - Design |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Connect the sidewalk system on east side of Brandon Mill Road from existing sidewalk to Lost Forest Dr |
| Construction Firm Selected | CMES |
| Design Firm Selected | Atkins |
| Estimated Design Completion Date | March, 2019 |
| Estimated Start Date For Project | October, 2017 |
| Estimated Construction Completion Date | March, 2022 |
| Estimated Substantial Completion Date | March, 2022 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,950,728 |
| TSPLOST Dollars Spent ($) | $1,725,047 |
| TSPLOST Dollars Committed (not spent) ($) | $225,681 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2022 |
| Last Update | 2024-10-18 16:02:43 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |