TSPLOSTProjects

Project ID CSS- 18
Local ID TS191
Project Name Title Mt Vernon Road and Johnson Ferry Road Intersection Improvements
Tier Tier 1
Project Type Congestion Relief
Initiatve Type TSPLOST
City Sandy Springs
Current Stage Construction
Project Description Operation and Safety improvements near the intersection of Mt. Vernon Hwy and Johnson Ferry Road.
Construction Firm Selected Vertical Earth
Design Firm Selected Jacobs
Estimated Design Completion Date December, 2022
Estimated Start Date For Project May, 2017
Estimated Construction Completion Date May, 2026
Estimated Substantial Completion Date April, 2026
Link To External Website http://spr.gs/jfmv
Primary Funding Source Sales Tax
TSPLOST Budget ($) $27,300,000
TSPLOST Dollars Spent ($) $19,596,575
TSPLOST Dollars Committed (not spent) ($) $7,703,425
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2026
Last Update 2026-03-06 15:49:07
State NULL
Address NULL
Creation Date NULL