| Project ID | CSS- 17 |
| Local ID | TS136 |
| Project Name Title | Central Parkway Sidewalk Gap Fill |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Provided a 600 ft. sidewalk gap fill in Sandy Springs and Dunwoody along Central Parkway in the Perimeter district |
| Construction Firm Selected | GDP |
| Design Firm Selected | PCID/Dunwoody |
| Estimated Design Completion Date | February, 2018 |
| Estimated Start Date For Project | March, 2018 |
| Estimated Construction Completion Date | March, 2018 |
| Estimated Substantial Completion Date | March, 2018 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $15,899 |
| TSPLOST Dollars Spent ($) | $15,899 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2018 |
| Last Update | 2021-05-04 19:12:29 |