Project ID CSS- 11
Local ID TS105
Project Name Title Roswell Road at Grogans Ferry Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Sandy Springs
Current Stage Completed
Project Description Realignment of the intersection and installation of traffic signal. Access management on Roswell Road.
Construction Firm Selected Ohmshiv
Design Firm Selected Columbia Engnieering
Estimated Design Completion Date July, 2020
Estimated Start Date For Project February, 2018
Estimated Construction Completion Date April, 2023
Estimated Substantial Completion Date March, 2023
Link To External Website https://www.sandyspringsga.gov/roswell-roadgrogans-ferry-road-improvements
Primary Funding Source Sales Tax
TSPLOST Budget ($) $4,800,000
TSPLOST Dollars Spent ($) $4,765,529
TSPLOST Dollars Committed (not spent) ($) $34,471
Cost Status Green
Schedule Status Green
Status Active