| Project ID | CSS- 10 |
| Local ID | TS106 |
| Project Name Title | Northside Dr. at Riverview Dr.-Old Powers Ferry Rd. |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Realignment of the intersection and a possible roundabout with sidewalk improvements. |
| Construction Firm Selected | Vertical Earth |
| Design Firm Selected | HNTB |
| Estimated Design Completion Date | May, 2021 |
| Estimated Start Date For Project | September, 2018 |
| Estimated Construction Completion Date | August, 2024 |
| Estimated Substantial Completion Date | March, 2024 |
| Link To External Website | http://spr.gs/riverview |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $4,402,748 |
| TSPLOST Dollars Spent ($) | $3,660,367 |
| TSPLOST Dollars Committed (not spent) ($) | $742,381 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2024 |
| Last Update | 2025-02-28 09:05:10 |