TSPLOSTProjects

Project ID CSS- 8
Local ID TS110
Project Name Title Mount Paran Road at Powers Ferry Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Sandy Springs
Current Stage Completed
Project Description Roundabout Design
Construction Firm Selected NULL
Design Firm Selected Arcadis
Estimated Design Completion Date December, 2019
Estimated Start Date For Project June, 2017
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $346,739
TSPLOST Dollars Spent ($) $346,739
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Green
Schedule Status Green
Status Inactive
Editor ajohnson@sandyspringsga.gov
Project Year NULL
Last Update 2022-07-29 17:53:15
State NULL
Address NULL
Creation Date NULL