TSPLOSTProjects

Project ID ROS- 5
Local ID NULL
Project Name Title Rucker Road Complete Street
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Roswell
Current Stage Completed
Project Description Reconstruction of Rucker Road from Roswell/Alpharetta City Limit boundary to GA-140/Arnold Mill Road/Houze Road Intersection. The project will include the addition of a multi-use path and sidewalk enhancements. Funding spent may include funds paid to contractors/consultants or indicate encumbered funds set aside for future payments.
Construction Firm Selected CW Matthews
Design Firm Selected TY Lynn
Estimated Design Completion Date December, 2018
Estimated Start Date For Project March, 2019
Estimated Construction Completion Date April, 2021
Estimated Substantial Completion Date April, 2021
Link To External Website https://www.roswellgov.com/government/departments/transportation/t-splost-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,264,327
TSPLOST Dollars Spent ($) $2,090,663
TSPLOST Dollars Committed (not spent) ($) $173,664
Cost Status Red
Schedule Status Green
Status Active
Editor dcox@roswellgov.com
Project Year NULL
Last Update 2023-04-14 16:18:26
State NULL
Address NULL
Creation Date NULL