Project ID ROS- 4
Local ID NULL
Project Name Title Highway 9 Gateway
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Roswell
Current Stage Land
Project Description Reconstruction of SR 9 from the Chattahoochee River north to Historic Roswell Square at SR 120 / Marietta Highway with new connections to the National Park Service Vickery Creek Unit. The project will remove the old reversible lane signal system and add one new lane in the off-peak direction so the roadway will have two lanes in each direction at all times. The project will new roundabouts and grade separate the intersection of SR 9 and Riverside Road / Azalea Drive. The majority of the roadway project is being funded by Federal and State funds from GDOT. Funding spent may include funds paid to contractors/consultants or indicate encumbered funds set aside for future payments. GDOT is currently doing right-of-way acquisition on the project.
Construction Firm Selected NULL
Design Firm Selected WSP
Estimated Design Completion Date May, 2023
Estimated Start Date For Project NULL
Estimated Construction Completion Date December, 2025
Estimated Substantial Completion Date NULL
Link To External Website https://www.roswellgov.com/government/departments/transportation/t-splost-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $3,000,000
TSPLOST Dollars Spent ($) $176,640
TSPLOST Dollars Committed (not spent) ($) $2,823,360
Cost Status Green
Schedule Status Green
Status Active