TSPLOSTProjects

Project ID FA- 47
Local ID 26-005
Project Name Title Harris Road Full-Depth Reclamation
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City Fairburn
Current Stage Construction
Project Description Prior to putting the project out to bid, the City of Fairburn requested funding assistance from the South Fulton CID to help deliver the Harris Road Full-Depth Reclamation Project. The CID agreed to pay $300,000 toward the construction of the project, with the understanding that Green Oil would cover the balance of the funding required to complete the construction. The agreement was subsequently formalized through an approves Intergovernmental Agreement (IGA). Through an approved Memorandum of Understanding (MOU), Green Oil agreed to reimburse and provide upfront funding for the Project Advertisement, Preliminary Engineering and Design Services, Construction Management, Project Management, and the Construction Engineering and Inspection (CEI) Services costs associated with the Project for a total of $107,925 in total project funding. The Invitation for Bid (IFB) for the Harris Road Full-Depth Reclamation Project was advertised on April 22nd, 2026. The bid opening date was May 22nd, 2026. The bid of the lowest responsive and responsible bidder came in at $369,725.75. Mayor and Council approved the Contract Award to Blount Construction Company, Inc. for the Harris Road Full-Depth Reclamation Project for the bid amount of $369,725.75 at the July 13th, 2026, City Council Meeting. The project entails full depth reclamation, asphalt paving and striping on Harris Road, from just west of Shortleaf Road (the Fairburn Family Travel Center Truck Stop exit) to the Senoia Road (SR74) Right-of-Way Limits. All work must be completed within sixty (60) calendar days of the Notice to Proceed with Construction (NTP). The first ($300,000) in project expenditures will come out of account number (360-0000-54-1421) T-SPLOST Fund, SFCID – Harris Road FDR. The remaining project expenditures ($69,725.75) will come out of account number (360-0000-52-1410) TSPLOST Fund, Infrastructure - Roadway.
Construction Firm Selected Blount Construction Company, Inc.
Design Firm Selected Atlas Technical Consultants
Estimated Design Completion Date March, 2026
Estimated Start Date For Project September, 2026
Estimated Construction Completion Date October, 2026
Estimated Substantial Completion Date October, 2026
Link To External Website Fairburn
Primary Funding Source Sales Tax
TSPLOST Budget ($) $369,726
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $369,726
Cost Status Green
Schedule Status NULL
Status Active
Editor lthompson@fairburn.com
Project Year 2026
Last Update 2026-09-02 13:00:04
State GA
Address City of Fairburn
Creation Date 2026-09-01