Project ID FA- 45
Local ID NULL
Project Name Title White Mill Road Full-Depth Reclamation
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City Fairburn
Current Stage Completed
Project Description The Full-Depth Reclamation of White Mill Road from SR 92 (Campbellton-Fairburn Road) to Rivertown Road, which is mostly with the City of South Fulton and partially inside the City of Fairburn. Through an IGA the City of South Fulton covered $1,270,558.31, and the City of Fairburn covered 158,400.
Construction Firm Selected Atlanta Paving & Concrete Construction, Inc.
Design Firm Selected NULL
Estimated Design Completion Date NULL
Estimated Start Date For Project January, 2023
Estimated Construction Completion Date June, 2023
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $816,700
TSPLOST Dollars Spent ($) $158,400
TSPLOST Dollars Committed (not spent) ($) $658,300
Cost Status Green
Schedule Status Green
Status Active
Editor lthompson@fairburn.com
Project Year 2023
Last Update 2026-08-31 11:57:27