| Project ID | FA- 45 |
| Local ID | NULL |
| Project Name Title | White Mill Road Full-Depth Reclamation |
| Tier | Tier 1 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST2 |
| City | Fairburn |
| Current Stage | Completed |
| Project Description | The Full-Depth Reclamation of White Mill Road from SR 92 (Campbellton-Fairburn Road) to Rivertown Road, which is mostly with the City of South Fulton and partially inside the City of Fairburn. Through an IGA the City of South Fulton covered $1,270,558.31, and the City of Fairburn covered 158,400. |
| Construction Firm Selected | Atlanta Paving & Concrete Construction, Inc. |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | NULL |
| Estimated Start Date For Project | January, 2023 |
| Estimated Construction Completion Date | June, 2023 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $816,700 |
| TSPLOST Dollars Spent ($) | $158,400 |
| TSPLOST Dollars Committed (not spent) ($) | $658,300 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | lthompson@fairburn.com |
| Project Year | 2023 |
| Last Update | 2026-08-31 11:57:27 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |