TSPLOSTProjects

Project ID ROS- 2
Local ID NULL
Project Name Title Big Creek Parkway
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Roswell
Current Stage Design
Project Description This project is being constructed in 2 Phases. Phase 1 will widen Warsaw Road near Holcomb Bridge Road (SR 140) and add New (dual) left turn lanes on SR 140 Holcomb Bridge Road turning onto Warsaw Road. The project will also add new dual left turn lanes from southbound Warsaw Road turning left onto Holcomb Bridge Road eastbound. Phase 1 construction began in Spring 2021 and utility work is underway. Phase 1 of the project is currently on schedule and on budget. Phase 2 will construct a new two-lane Complete Street Roadway including bike lanes, sidewalks, and multi-use path from Warsaw Road moving east on new alignment before crossing over GA-400 and then connecting to Old Alabama Road near Holcomb Woods Parkway. Design on Phase 2 is continuing and Construction is anticipated to begin in 2023. Funding spent may include funds paid to contractors/consultants or indicate encumbered funds set aside for future payments. Phase 2 is currently more than 90 days behind schedule. In December of 2023, the Mayor and Council voted to modify the project alignment back to the original 2016 alignment.
Construction Firm Selected NULL
Design Firm Selected Gresham Smith and Partners
Estimated Design Completion Date December, 2026
Estimated Start Date For Project April, 2027
Estimated Construction Completion Date December, 2030
Estimated Substantial Completion Date NULL
Link To External Website https://www.roswellgov.com/government/departments/transportation/t-splost-projects
Primary Funding Source Sales Tax
TSPLOST Budget ($) $43,536,802
TSPLOST Dollars Spent ($) $5,598,604
TSPLOST Dollars Committed (not spent) ($) $37,938,198
Cost Status Red
Schedule Status Red
Status Active
Editor dcox@roswellgov.com
Project Year NULL
Last Update 2024-03-05 17:03:04
State NULL
Address NULL
Creation Date NULL