Project ID FA- 41
Local ID 24-009
Project Name Title Cleckler Rd Full-Depth Reclamation Project
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City Fairburn
Current Stage Completed
Project Description Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The total project costs were $445,687.77. The South Fulton CID covered first $209,041.09 in construction costs, the remaining $236,646.68 in construction costs was paid for with TSPLOST Funds.
Construction Firm Selected BLOUNT CONSTRUCTION
Design Firm Selected SOUTHEASTERN ENGINEERING INC.
Estimated Design Completion Date May, 2024
Estimated Start Date For Project July, 2024
Estimated Construction Completion Date November, 2024
Estimated Substantial Completion Date October, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $209,041
TSPLOST Dollars Spent ($) $239,647
TSPLOST Dollars Committed (not spent) ($) $-30,606
Cost Status Green
Schedule Status Green
Status Active
Editor lthompson@fairburn.com
Project Year 2024
Last Update 2026-08-31 11:55:35
State GA
Address Cleckler Rd.
Creation Date 2025-05-06