TSPLOSTProjects

Project ID FA- 41
Local ID 24-009
Project Name Title Cleckler Rd Full-Depth Reclamation Project
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST2
City Fairburn
Current Stage Bidding
Project Description Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments.
Construction Firm Selected BLOUNT CONSTRUCTION
Design Firm Selected SOUTHEASTERN ENGINEERING INC.
Estimated Design Completion Date May, 2024
Estimated Start Date For Project July, 2024
Estimated Construction Completion Date November, 2024
Estimated Substantial Completion Date October, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $209,041
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $209,041
Cost Status Green
Schedule Status Green
Status Active
Editor anthony.belcher@fairburn.com
Project Year 2024
Last Update 2025-08-04 16:18:35
State GA
Address Cleckler Rd.
Creation Date 2025-05-06