| Project ID | JCR- 53 |
| Local ID | TS0250 |
| Project Name Title | Town Center - Pedestrian Crossing |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST2 |
| City | Johns Creek |
| Current Stage | Completed |
| Project Description | Pedestrian crossing on SR 141/ Medlock Bridge Road in the Town Center redevelopment area. |
| Construction Firm Selected | Vertical Earth |
| Design Firm Selected | Michael Baker |
| Estimated Design Completion Date | September, 2024 |
| Estimated Start Date For Project | November, 2024 |
| Estimated Construction Completion Date | July, 2026 |
| Estimated Substantial Completion Date | July, 2026 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $6,000,000 |
| TSPLOST Dollars Spent ($) | $7,913,355 |
| TSPLOST Dollars Committed (not spent) ($) | $-1,913,355 |
| Cost Status | Red |
| Schedule Status | Yellow |
| Status | Inactive |
| Editor | brian.oconnor@johnscreekga.gov |
| Project Year | NULL |
| Last Update | 2026-08-17 16:53:47 |
| State | Georgia |
| Address | City of Johns Creek |
| Creation Date | 2022-03-31 |