Project ID JCR- 43
Local ID TS0230
Project Name Title Town Center - Main Street (Lakefield Drive)
Tier Tier 1
Project Type Landscape and Streetscape
Initiatve Type TSPLOST2
City Johns Creek
Current Stage Land
Project Description Landscaping along Main Street/Lakefield Drive within Johns Creek Town Center redevelopment.
Construction Firm Selected NULL
Design Firm Selected Kimley-Horn
Estimated Design Completion Date September, 2026
Estimated Start Date For Project November, 2026
Estimated Construction Completion Date May, 2028
Estimated Substantial Completion Date May, 2028
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,000,000
TSPLOST Dollars Spent ($) $224,000
TSPLOST Dollars Committed (not spent) ($) $1,776,000
Cost Status Green
Schedule Status Green
Status Active
Editor brian.oconnor@johnscreekga.gov
Project Year NULL
Last Update 2026-08-17 16:35:13
State Georgia
Address City of Johns Creek
Creation Date 2022-03-31