TSPLOSTProjects

Project ID CSS- 67
Local ID S2184
Project Name Title Jett Ferry Road/Spalding Drive (Jett Ferry Court to Dunvegan Close)
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Construction
Project Description Jett Ferry Road/Spalding Drive (Jett Ferry Court to Dunvegan Close)
Construction Firm Selected Sol Construction
Design Firm Selected Kimley Horn
Estimated Design Completion Date June, 2026
Estimated Start Date For Project December, 2021
Estimated Construction Completion Date September, 2026
Estimated Substantial Completion Date September, 2026
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $700,000
TSPLOST Dollars Spent ($) $148,431
TSPLOST Dollars Committed (not spent) ($) $551,569
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2026
Last Update 2026-03-06 15:44:03
State NULL
Address 3245 Spalding Dr, Sandy Springs, GA 30350
Creation Date NULL