| Project ID | CSS- 63 |
| Local ID | S2163 |
| Project Name Title | Northland Drive (Landmark Drive to Ex. SW at Northland Ridge Trail) |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST2 |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Northland Drive (Landmark Drive to Ex. SW at Northland Ridge Trail) |
| Construction Firm Selected | Construction 57 |
| Design Firm Selected | Heath & Lineback |
| Estimated Design Completion Date | April, 2024 |
| Estimated Start Date For Project | December, 2022 |
| Estimated Construction Completion Date | November, 2024 |
| Estimated Substantial Completion Date | October, 2024 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $195,000 |
| TSPLOST Dollars Spent ($) | $176,156 |
| TSPLOST Dollars Committed (not spent) ($) | $18,844 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2024 |
| Last Update | 2025-06-18 16:19:56 |
| State | NULL |
| Address | 4906 Northland Dr, Atlanta, GA 30342 |
| Creation Date | NULL |