Project ID CSS- 63
Local ID S2163
Project Name Title Northland Drive (Landmark Drive to Ex. SW at Northland Ridge Trail)
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Completed
Project Description Northland Drive (Landmark Drive to Ex. SW at Northland Ridge Trail)
Construction Firm Selected Construction 57
Design Firm Selected Heath & Lineback
Estimated Design Completion Date April, 2024
Estimated Start Date For Project December, 2022
Estimated Construction Completion Date November, 2024
Estimated Substantial Completion Date October, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $195,000
TSPLOST Dollars Spent ($) $176,156
TSPLOST Dollars Committed (not spent) ($) $18,844
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2024
Last Update 2025-06-18 16:19:56
State NULL
Address 4906 Northland Dr, Atlanta, GA 30342
Creation Date NULL