| Project ID | EP- 5 |
| Local ID | EP-177 |
| Project Name Title | Washington Road Sidewalk |
| Tier | Tier 1 |
| Project Type | Pedestrian Improvements |
| Initiatve Type | TSPLOST |
| City | East Point |
| Current Stage | Construction |
| Project Description | The Project was bid Out for Construction. The lowest apparent bidder was DAF Concrete. Project is for new installation of sidewalk along the Washington Road corridor from I-285 to Delowe Drive. |
| Construction Firm Selected | DAF Concrete, LLC |
| Design Firm Selected | Moreland Altobelli (ATLAS) |
| Estimated Design Completion Date | June, 2018 |
| Estimated Start Date For Project | June, 2021 |
| Estimated Construction Completion Date | June, 2022 |
| Estimated Substantial Completion Date | June, 2022 |
| Link To External Website | http://www.eastpointcity.org |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,993,420 |
| TSPLOST Dollars Spent ($) | $322,000 |
| TSPLOST Dollars Committed (not spent) ($) | $1,671,420 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | Cadell Hall |
| Project Year | 2021 |
| Last Update | 2021-10-11 22:09:50 |