| Project ID | CSS- 62 |
| Local ID | S2168 |
| Project Name Title | Hilderbrand Police gym to Roswell Road (both sides) |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST2 |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Hilderbrand Police gym to Roswell Road (both sides) |
| Construction Firm Selected | Zaveri |
| Design Firm Selected | NV5 |
| Estimated Design Completion Date | February, 2025 |
| Estimated Start Date For Project | December, 2022 |
| Estimated Construction Completion Date | August, 2025 |
| Estimated Substantial Completion Date | July, 2025 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $520,000 |
| TSPLOST Dollars Spent ($) | $442,270 |
| TSPLOST Dollars Committed (not spent) ($) | $77,730 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2025 |
| Last Update | 2025-12-11 08:39:33 |
| State | NULL |
| Address | 218 Hilderbrand Dr, Atlanta, GA 30328 |
| Creation Date | NULL |