Project ID CSS- 60
Local ID S2177
Project Name Title Powers Ferry Road (New Northside Drive to 6201 Powers Ferry Road)
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Completed
Project Description Powers Ferry Road (New Northside Drive to 6201 Powers Ferry Road)
Construction Firm Selected Vertical Earth
Design Firm Selected NV5
Estimated Design Completion Date September, 2023
Estimated Start Date For Project December, 2022
Estimated Construction Completion Date February, 2025
Estimated Substantial Completion Date December, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $385,000
TSPLOST Dollars Spent ($) $278,960
TSPLOST Dollars Committed (not spent) ($) $106,040
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2025
Last Update 2025-06-18 16:23:24
State NULL
Address 6201 Powers Ferry Rd NW, Sandy Springs, GA 30339