TSPLOSTProjects

Project ID CSS- 56
Local ID S2161
Project Name Title Windsor Parkway Sidewalk - Gap Fills
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Bidding
Project Description Windsor Parkway Sidewalk - Gap Fills
Construction Firm Selected NULL
Design Firm Selected NV5
Estimated Design Completion Date July, 2026
Estimated Start Date For Project January, 2023
Estimated Construction Completion Date December, 2027
Estimated Substantial Completion Date December, 2027
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,725,000
TSPLOST Dollars Spent ($) $274,517
TSPLOST Dollars Committed (not spent) ($) $1,450,483
Cost Status Green
Schedule Status Green
Status Active
Editor cschultz@sandyspringsga.gov
Project Year 2027
Last Update 2026-09-02 10:03:12
State NULL
Address 575 Windsor Pkwy, Atlanta, GA 30342
Creation Date NULL