Project ID CSS- 54
Local ID S2175
Project Name Title Trowbridge Road Sidewalk (Spalding Trail to Trowbridge Lake Drive)
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Completed
Project Description Trowbridge Road Sidewalk (Spalding Trail to Trowbridge Lake Drive)
Construction Firm Selected Blount Construction
Design Firm Selected NV5
Estimated Design Completion Date October, 2024
Estimated Start Date For Project December, 2022
Estimated Construction Completion Date April, 2024
Estimated Substantial Completion Date April, 2024
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $95,000
TSPLOST Dollars Spent ($) $50,985
TSPLOST Dollars Committed (not spent) ($) $44,015
Cost Status Green
Schedule Status Green
Status Active
Editor ajohnson@sandyspringsga.gov
Project Year 2024
Last Update 2024-07-22 13:47:37
State NULL
Address 7445 Trowbridge Rd, Sandy Springs, GA 30328
Creation Date NULL