| Project ID | CSS- 53 |
| Local ID | S2188-1 |
| Project Name Title | Allen Road at Sandy Springs Circle |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST2 |
| City | Sandy Springs |
| Current Stage | Completed |
| Project Description | Gap Fill Sidewalks |
| Construction Firm Selected | Blount Construction |
| Design Firm Selected | NV5 |
| Estimated Design Completion Date | NULL |
| Estimated Start Date For Project | January, 2023 |
| Estimated Construction Completion Date | November, 2023 |
| Estimated Substantial Completion Date | November, 2023 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $55,000 |
| TSPLOST Dollars Spent ($) | $19,125 |
| TSPLOST Dollars Committed (not spent) ($) | $35,875 |
| Cost Status | Green |
| Schedule Status | NULL |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2023 |
| Last Update | 2024-03-29 14:22:20 |
| State | NULL |
| Address | 1 Allen Rd NE, Sandy Springs, GA 30328 |
| Creation Date | NULL |