| Project ID | CSF- 338 |
| Local ID | OSI 631 |
| Project Name Title | Union / Thames |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST2 |
| City | City of South Fulton |
| Current Stage | Design |
| Project Description | The T-intersection with a Stop control was analyzed for traffic improvements and a realignment was selected. Additional improvements include drainage, 2.5 ft. of curb & gutter, 2 ft. stamped concrete buffer, and 5 ft. and 10 ft. sidewalks. Streetlights will be installed within the project limits.? |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | April, 2027 |
| Estimated Start Date For Project | April, 2024 |
| Estimated Construction Completion Date | October, 2028 |
| Estimated Substantial Completion Date | October, 2028 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $194,700 |
| TSPLOST Dollars Spent ($) | $82,285 |
| TSPLOST Dollars Committed (not spent) ($) | $112,415 |
| Cost Status | NULL |
| Schedule Status | NULL |
| Status | Active |
| Editor | roussan.francois@cityofsouthfultonga.gov |
| Project Year | 2025 |
| Last Update | 2026-09-22 09:48:10 |
| State | NULL |
| Address | NULL |
| Creation Date | 2022-05-13 |