TSPLOSTProjects

Project ID FA- 39
Local ID NULL
Project Name Title Oakley Industrial Boulevard Extension (Design Only)
Tier Tier 1
Project Type Roadway Projects
Initiatve Type TSPLOST2
City Fairburn
Current Stage Design
Project Description The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullatt Road. The project design is approximately 90% complete. The South Fulton Community Improvement District (CID) is covering the project's design costs. The City of Fairburn expended approximately $15,823 in TSPLOST Funds on a Task Order with Atlas Technical Consultants for roadway staking and subsurface exploration to investigate the soil conditions for excavation purposes at the proposed Oakley Industrial Boulevard Extension between stations 104+00, 105+00, 108+00, 109+00, 110+00, and 111+00. The project is currently in the ROW Acquisition Phase. There is a total of nine (9) parcels, with five (5) parcels remaining. This phase is holding up the project due to a stalemate in negotiations, making it significantly behind schedule. The most recent rough construction cost estimate is $4,950,000.00 as of 1/22/2026.
Construction Firm Selected NULL
Design Firm Selected SOUTHEASTERN ENGINEERING INC.
Estimated Design Completion Date March, 2027
Estimated Start Date For Project October, 2027
Estimated Construction Completion Date December, 2028
Estimated Substantial Completion Date October, 2028
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $0
TSPLOST Dollars Spent ($) $15,823
TSPLOST Dollars Committed (not spent) ($) $-15,823
Cost Status Green
Schedule Status Red
Status Active
Editor lthompson@fairburn.com
Project Year NULL
Last Update 2026-08-31 11:46:25
State Georgia
Address Oakley Industrial Boulevard
Creation Date 2022-03-31