| Project ID | FA- 39 |
| Local ID | NULL |
| Project Name Title | Oakley Industrial Boulevard Extension (Design Only) |
| Tier | Tier 1 |
| Project Type | Roadway Projects |
| Initiatve Type | TSPLOST2 |
| City | Fairburn |
| Current Stage | Design |
| Project Description | The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullatt Road. The project design is approximately 90% complete. The South Fulton Community Improvement District (CID) is covering the project's design costs. The City of Fairburn expended approximately $15,823 in TSPLOST Funds on a Task Order with Atlas Technical Consultants for roadway staking and subsurface exploration to investigate the soil conditions for excavation purposes at the proposed Oakley Industrial Boulevard Extension between stations 104+00, 105+00, 108+00, 109+00, 110+00, and 111+00. The project is currently in the ROW Acquisition Phase. There is a total of nine (9) parcels, with five (5) parcels remaining. This phase is holding up the project due to a stalemate in negotiations, making it significantly behind schedule. The most recent rough construction cost estimate is $4,950,000.00 as of 1/22/2026. |
| Construction Firm Selected | NULL |
| Design Firm Selected | SOUTHEASTERN ENGINEERING INC. |
| Estimated Design Completion Date | March, 2027 |
| Estimated Start Date For Project | October, 2027 |
| Estimated Construction Completion Date | December, 2028 |
| Estimated Substantial Completion Date | October, 2028 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $0 |
| TSPLOST Dollars Spent ($) | $15,823 |
| TSPLOST Dollars Committed (not spent) ($) | $-15,823 |
| Cost Status | Green |
| Schedule Status | Red |
| Status | Active |
| Editor | lthompson@fairburn.com |
| Project Year | NULL |
| Last Update | 2026-08-31 11:46:25 |
| State | Georgia |
| Address | Oakley Industrial Boulevard |
| Creation Date | 2022-03-31 |