TSPLOSTProjects

Project ID EP- 3
Local ID EP-123
Project Name Title Oakleigh Drive Improvements
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City East Point
Current Stage Completed
Project Description This project within an industrial warehouse district, consisting of road resurfacing and new sidewalk installation.
Construction Firm Selected BRTU Construction
Design Firm Selected NULL
Estimated Design Completion Date NULL
Estimated Start Date For Project May, 2018
Estimated Construction Completion Date August, 2018
Estimated Substantial Completion Date July, 2018
Link To External Website http://www.eastpointcity.org
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,300,000
TSPLOST Dollars Spent ($) $1,300,000
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Green
Schedule Status Green
Status Active