| Project ID | CSS- 44 |
| Local ID | S2193 |
| Project Name Title | Hammond Drive Widening |
| Tier | Tier 1 |
| Project Type | Congestion Relief |
| Initiatve Type | TSPLOST2 |
| City | Sandy Springs |
| Current Stage | Land |
| Project Description | Project provides multi-modal opportunities within the approximately 0.75 mile corridor between Boylston Drive and Glenridge Drive including increased vehicular capacity, roundabouts, transit/shuttle provisions, multi-use trails, sidewalks, wide median, and other attributes. |
| Construction Firm Selected | NULL |
| Design Firm Selected | Gresham Smith |
| Estimated Design Completion Date | August, 2025 |
| Estimated Start Date For Project | June, 2022 |
| Estimated Construction Completion Date | June, 2029 |
| Estimated Substantial Completion Date | June, 2029 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $35,000,000 |
| TSPLOST Dollars Spent ($) | $11,874,378 |
| TSPLOST Dollars Committed (not spent) ($) | $23,125,622 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | ajohnson@sandyspringsga.gov |
| Project Year | 2029 |
| Last Update | 2026-03-06 15:48:01 |
| State | Georgia |
| Address | Hammond Drive |
| Creation Date | 2022-03-31 |