Project ID CSS- 36
Local ID S2104
Project Name Title Boylston Drive Sidepath & Realignment
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Sandy Springs
Current Stage Construction
Project Description Intersection and streetscape improvements from Hammond Drive to Hilldebrand Drive.
Construction Firm Selected Excellere
Design Firm Selected NV5
Estimated Design Completion Date November, 2024
Estimated Start Date For Project October, 2019
Estimated Construction Completion Date March, 2025
Estimated Substantial Completion Date March, 2025
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $0
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Green
Schedule Status Green
Status Inactive
Editor ajohnson@sandyspringsga.gov
Project Year 2025
Last Update 2025-12-11 08:32:32
State Georgia
Address Boylston Drive