TSPLOSTProjects

Project ID ROS- 23
Local ID NULL
Project Name Title Cox Road Intersection Improvements (at Etris Rd and at King Rd)
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Roswell
Current Stage Concept
Project Description Project will construct new intersection improvements on Cox Road at both King Road and at Etris Road.. Per Agreement with City of Milton, Milton is lead on project
Construction Firm Selected NULL
Design Firm Selected Pond
Estimated Design Completion Date NULL
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website https://www.roswellgov.com/government/departments/transportation/tsplost2
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,000,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $1,000,000
Cost Status Green
Schedule Status Green
Status Active
Editor dcox@roswellgov.com
Project Year NULL
Last Update 2024-03-05 17:11:41
State Georgia
Address Cox Road
Creation Date 2022-03-31