TSPLOSTProjects

Project ID ROS- 20
Local ID NULL
Project Name Title Corridor Improvements for Grimes Bridge, Dogwood, Old Dogwood Roads
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City Roswell
Current Stage Design
Project Description The project will examine the feasibility of improvements to both Grimes Bridge Road and portions of Dogwood Road. Potential improvements may include new multi-use trail, sidewalks, or intersection improvements
Construction Firm Selected NULL
Design Firm Selected NV5
Estimated Design Completion Date July, 2025
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website https://www.roswellgov.com/government/departments/transportation/tsplost2
Primary Funding Source Sales Tax
TSPLOST Budget ($) $10,500,000
TSPLOST Dollars Spent ($) $783,813
TSPLOST Dollars Committed (not spent) ($) $9,716,187
Cost Status Green
Schedule Status Green
Status Active
Editor mdana@roswellgov.com
Project Year NULL
Last Update 2026-10-01 11:17:12
State Georgia
Address Grimes Bridge
Creation Date 2022-03-31