| Project ID | ROS- 19 |
| Local ID | NULL |
| Project Name Title | Nesbit Ferry Rd ΓÇô Corridor Improvement with Johns Creek |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST2 |
| City | Roswell |
| Current Stage | Concept |
| Project Description | Project will construct new operational improvements and some pedestrian facilities in various locations between SR-140/Holcomb Bridge Road and a point near Old Alabama Road in Johns Creek. The project runs along the city boundary between Roswell and Johns Creek. City of Johns Creek is the lead on the project and is paying the majority of the project costs, Roswell's share is only $1,000,000 million. |
| Construction Firm Selected | NULL |
| Design Firm Selected | Practical Design Partners |
| Estimated Design Completion Date | NULL |
| Estimated Start Date For Project | NULL |
| Estimated Construction Completion Date | NULL |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | https://www.roswellgov.com/government/departments/transportation/tsplost2 |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,000,000 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $1,000,000 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | dcox@roswellgov.com |
| Project Year | NULL |
| Last Update | 2023-08-04 11:25:11 |
| State | Georgia |
| Address | Nesbit Ferry Rd |
| Creation Date | 2022-03-31 |